Two City of Yonkers offices decide most concrete permits: the Department of Housing and Buildings issues building permits, and the Engineering Department issues permits for work in the City's right-of-way, the strip of public street, curb and sidewalk. A new driveway can need both. By the City's own FAQ, repaving inside an area the City already approved needs no building permit; by its property owner page, any sidewalk repair needs an Engineering permit first. Above the City sit the State of New York's contract law, one-call rule and sales tax; Westchester County's Department of Consumer Protection adds advice on hiring a contractor. This guide quotes the Code of the City of Yonkers, as eCode360 publishes it with legislation through 10-28-2025, and the City's FAQ answers word for word, each with its section number.
A City FAQ answer lists what that building department enforces: the Yonkers Zoning Ordinance, which took effect on December 9, 2000, the City's building, housing, plumbing and fire codes, 'and the Codes of New York State.' New York City's sidewalk and building rules carry no weight here, since the City of Yonkers is a separate city in Westchester County under its own Code. Every fee, deposit and penalty below comes with its Code section or fee document and its date; what the concrete itself costs is on our Yonkers concrete cost page. Where a source is silent, we say so and name the office that decides. This page reports what the sources say and is not legal advice. Our written quote for a job names the permits that job needs.
Which concrete jobs need a City of Yonkers building permit
In the Code of the City of Yonkers, section 56-15A sets the base rule: no one may begin 'the construction, enlargement, alteration, improvement, removal or demolition of any building or structure' until the Department of Housing and Buildings has issued its permit (amended 7-18-1996 by L.L. No. 5-1996). Section 56-15B exempts 'necessary repairs which do not materially affect structural features', though not work that cuts walls, removes beams or supports, or changes stairways or required exits. In its guide to administering the Uniform Code, revised 2026, the State's Department of State lets local programs exclude some work from permits; its list names no driveways, sidewalks, patios or retaining walls, which leaves those to the City's own law, and excluded work 'still must conform to all applicable provisions of the Uniform Code and Energy Code.' The City's wording is in Chapter 56's permit and fee sections.
The City's building permit FAQ settles driveways in its own words. Asked whether creating a driveway and off-street parking space needs a permit, it answers: 'Yes. There are many requirements that you will need to comply with if you are creating a new parking space/area'. It adds: 'you will need a building permit from the Department of Housing and Buildings.' Work 'within the City's right-of-way (R.O.W.)' also takes the Engineering Department's curb-cut permit. The FAQ asks for 'the location of the parking space, the driveway grade (% slope),' 'the finish of the surface area, and how you intend to drain it.' Repaving gets the opposite answer: 'No. If you do not add to the areas already approved you may repave without a building permit.' Our page on concrete driveways in Yonkers covers the slab itself.
Two FAQ answers leave gaps that the Department of Housing and Buildings fills. The patio answer exempts small new patios but does not say what a larger one needs, and it warns that 'there are certain Zoning requirements that restrict the location and size of the patio'. The fence answer is 'No', yet section 56-19A(6) of the City code still prints a fence fee, so confirm a fence with the Department before work starts. The exemption in section 56-52, the City's excavation permit, turns on the words 'other than for the construction of a wall, driveway, sidewalk, building or part thereof', and the Department decides how that clause applies to a given cut. For anything these answers leave open, the FAQ's own advice is 'When in doubt-ask!'
- Patios: 'New Patios less than or equal to 200 square feet do not require a permit.' (City of Yonkers building permit FAQ)
- Decks: a permit is required, because 'A deck is a structural system that must be evaluated for compliance with the City of Yonkers Zoning Ordinance', while 'A patio is placed on the surface of the ground.' (same FAQ)
- Fences: no permit under the FAQ, which caps height at 'a maximum of four feet in height in any yard fronting a street' and six feet in a side or rear yard.
- Sheds: the FAQ requires a permit; under City code section 56-95D, a letter permit covers the smallest ones, up to eight feet by 10 feet, no shed may exceed 11 feet by 12 feet, and sheds go only in side or rear yards.
- Facades: 'Yes, All facade repairs, restoration, or pointing requires a Building Permit.' (FAQ)
- Excavation or fill: City code section 56-52 requires a separate permit 'Before any excavation or filling operation which exceeds 60 cubic yards', and section 56-54A sets a minimum fee of $1,000 for up to 20,000 cubic yards of excavation (last amended 5-14-2019).
- Landmarks and historic districts: City code section 45-8A requires a certificate of appropriateness for 'Any alteration or repair which causes any material change in appearance' of a designated landmark or of a feature in a designated historic district; Chapter 45 does not name steps, walks or paving.
Applying for a Yonkers permit, the fees and the inspections
Building permit applications go to the Department of Housing and Buildings, either online through its City Squared filing portal or on paper by mail or drop-off. The City's undated checklist for paper filing asks for the plans as one signed and sealed PDF on a USB flash drive, an application form the property owner signs in front of a notary, a letter of authorization when someone other than the owner files, a management or board letter for co-ops and condos, and contractor insurance proof. An owner acting as contractor on an owner-occupied home of one to four families files a homeowner affidavit and hold harmless form instead. City code section 56-17B puts the estimated cost of the work on the sworn application, and the City's FAQ says the Code requires the permit to be displayed in a window.
Section 56-18 of the City's Code, amended 6-25-2025 by L.L. No. 3-2025, sets the permit fees. One- and two-family dwellings pay a '$125 filing fee plus $15 per each $1,000 of the estimated cost'; permits for anything else estimated below $10 million carry a '$250 filing fee plus $15 per each $1,000'. Nothing in the section prices driveways, patios, retaining walls or paving on a line of their own; its cost-based fee names alterations, decks, open structures, new buildings, additions and demolitions. Section 56-20A takes half the total when plans are filed and the rest when the permit is issued. Starting without a permit costs more: section 56-19.1B, amended 5-14-2019, adds 'a penalty of two times the total permit fee otherwise due' for each permit, and section 56-19.1 holds the permit until it is paid.
City inspections come before the work is hidden. Section 56-32A says 'Inspections shall occur prior to enclosing or covering the work to be inspected' and lists excavation and site preparation first, then 'Footings and foundation inspection, to be made after footing trenches are excavated and the necessary forms erected.' Section 56-32B(1) keeps reinforcing steel uncovered until it is inspected and approved. Calling for an inspection is up to the owner, applicant or agent under section 56-33, and the Commissioner must act on each request within two days; section 56-36 wants notice at least 48 hours before the final inspection. Under section 56-26A a permit expires within one year of issuance, and the Commissioner may revoke it when the foundation is still unfinished three months after issuance; section 56-26B allows renewals for periods of 90 days to one year.
- Reinspections and changes: '$250 and each subsequent reinspection shall be $500' (City code section 56-19C), and changing the contractor or design professional costs $150 (section 56-19D); section 56-19 was last amended 6-25-2025.
- Extensions: $100 for 12 months on a one- or two-family permit, per the Department's undated extension sheet; other permits pay 1/24 of the original fee per month plus $250, or $500 minimum (City code section 56-19B; section 56-19 last amended 6-25-2025).
- Withdrawn or denied applications: money paid above half the fee may be refunded 'less a $1,500 administrative fee' (City code section 56-20D, added 5-14-2019).
- Unpaid City or County property taxes: 'a building permit may be refused until the tax and all fees and interest have been paid' (City code section 56-15C, added 2-26-2013).
Sidewalks, curbs and aprons: the owner's duty and 30 days
A Yonkers property owner keeps up the sidewalk out front. Section 103-1 of the City's Code, part of the sidewalk article adopted 12-26-1911, places the walk in front of each lot on its owner, who must keep it 'at all times in good repair and in a safe condition for public use.' If the Commissioner of Public Works decides a walk needs repair, section 103-3 has a notice served personally or by registered mail, and the owner must act 'within 30 days from the service of such notice'. An owner who neglects or refuses gets the City's repair under section 103-4 and its bill under section 103-5. Section 103-128 treats a breach of that article as a Class II offense, with a civil penalty of $250 to $5,000 under section 1-21 (amended 6-26-2012). The sections are in the City's sidewalk repair article.
No sidewalk work starts without an Engineering Department permit. 'Owners must obtain a permit from the Engineering Department' ahead of any sidewalk repair or replacement, in the words of the City's property owner page. The Department wants the date you plan to start, in-person payment by check or money order made payable to the City, and liability coverage of one million dollars on file before it issues a sidewalk permit, with the Engineering Department added to the policy and named certificate holder; a homeowner's policy or a contractor's can hold it. Fees are on the Engineering Department's 2012 deposit and fee worksheet, which prints no effective date. Replacing an existing sidewalk or driveway carries a $200 deposit and a fee of $50 for 100 square feet or less, $100 between 100 and 500 square feet, or $250 over 500 square feet. Our sidewalk repair page covers the work.
Cutting or lowering a curb, or changing a sidewalk's grade, takes the City Engineer's permit under section 103-14 of the City's Code, and section 103-15 requires a written application from the owner of the abutting premises. Section 103-16A, amended 3-10-2015, grants no cut 'for a distance or length along any street, avenue or highway of more than 30 feet', none within 10 feet of any other section of curb that has been or is to be cut or lowered, and none at a corner; under section 103-16B the City Engineer may grant exceptions once the City Council has had 10 days' written notice. Section 103-21 reads: 'All private driveways crossing sidewalks shall be paved with concrete or other approved materials.' See the City's curb-cut article and our page on driveway aprons and curb cuts.
- Curb-cut fee: the 2012 worksheet charges a $500 deposit and $5 for each linear foot, $50 minimum, but City code section 103-17 has the City Engineer fix that fee with the Mayor's approval, so confirm the current amount with the Engineering Department.
- Restoration: under City code section 103-31A, walks and curbs injured by street work 'shall be restored by him to as good condition as that in which they were found.'
- Winter: on street openings, City code section 103-32 says 'no permanent pavement shall be restored between December 1 and April 1.'
- Specifications: the six-inch portland cement concrete patch in City code section 103-33D is a street-pavement standard; the City sections we cite set no sidewalk thickness or mix.
- City liability: under Charter section C24-11, a sidewalk defect claim cannot proceed against the City unless written notice of the condition had actually been given to the Commissioner of Public Works and the City did not repair it within a reasonable time.
- Owner liability: deciding a Yonkers trip case on April 26, 2017, New York's Appellate Division, Second Department, held that City code section 103-1 'does not impose tort liability upon them for injuries caused by a violation of that duty'.
- General rule: the same decision says liability for sidewalk defects 'is placed on the municipality, and not the abutting landowner', unless the owner created the defect, caused it by a special use of the walk, or broke a specific ordinance or statute obligating the owner to maintain it. That is one decision, not legal advice.
Snow, ice and salt: section 103-9 and new concrete
Section 103-9 of the City's Code sets the clock for a snowy walk: 'Snow and ice shall be removed from abutting fire hydrants and such sidewalks for the whole width thereof within six hours after every fall of snow which shall cease in the daytime and before 12:00 noon of the day after any fall of snow which may come in the nighttime.' Section 103-8, in the snow article amended in its entirety 2-25-2020, puts that duty on every owner or the owner's designee, vacant lots included, plus 'a three-foot area measured from the center line' of a hydrant. Section 103-9 also forbids sweeping, throwing or depositing snow or ice 'into any street, street gutter, or sidewalk'. The full text is in the City's snow and ice article.
Plowing and salting of City streets fall to the Street Maintenance Division of the Department of Public Works. Its snow page sets salt 'at least 300 pounds per lane mile', applies '15,000 gallons of brine with organics to the roadways' during a storm, and draws on a salt barn that holds 7,500 tons; it names salt and brine only, with no mention of sand or calcium chloride. Article XIV of Chapter 103, the City's deicing article adopted 6-23-2015, lets the Commissioner of Public Works set rules on 'proper application and spreader rates for all deicing materials' (section 103-125), and section 103-126 bans natural gas waste on any road or property in the City. Section 103-78 separately bars letting water from roofs run across a sidewalk, curbstone or gutter.
Salt does its worst damage to new concrete. The National Ready Mixed Concrete Association's CIP 2 defines scaling as 'local flaking or peeling of a finished surface of hardened concrete' and names among its causes the 'Application of excessive amounts of deicing chemicals, especially on newly installed concrete that tends to be saturated and of lower strength.' The sheet calls calcium chloride and sodium chloride (rock salt) acceptable for concrete, says ammonium sulfate, ammonium nitrate and magnesium-based salts 'are chemically aggressive and destroy concrete surfaces', and advises: 'Avoid the use of deicing chemicals in the first winter and subsequently use them in moderate amounts.' We ask the same of every owner whose new slab we pour. Freeze counts for Yonkers are on our weather and ground data page.
- Penalty: City code section 103-128 makes a breach of the snow article a Class III offense, subject under section 1-21 (amended 6-26-2012) to a fine of not more than $1,000 or a civil penalty of not more than $1,500.
- Uncleared walks: when an owner fails, City code section 103-10 allows the Commissioner of Public Works to clear the walk, and section 103-11 sends a certificate of the expense to the City Clerk.
- Plowing: the City's snow page adds, 'It is also a violation to shovel, blow, and plow snow into a city street.'
- Snow emergencies: under Chapter 108 of the City code, adopted 11-14-2017, the Mayor or a designee may declare one when snow, ice, sleet or freezing rain is expected; violations are Class II offenses (section 108-5).
- Air in the mix: the American Concrete Institute says entrained air helps 'to minimize the scaling that results from applications of chemicals for ice removal.'
- Driveway salt: NRMCA's CIP 2 also advises, 'When conditions permit, hose off accumulation of salt deposited by cars on driveways and garage slabs.'
Zoning limits on parking pads, patios, walls and work hours
Front-yard parking comes first in most Yonkers driveway plans. For one- and two-family homes, section 43-133A(1) of the City's Code keeps parking spaces 'within a building or in a side or rear yard.' The exception sits in paragraph (4) of that section, which makes room for 'a maximum of two private passenger vehicles' on a paved driveway 'constructed in accordance with a valid building permit', in four defined front-yard areas, one of them 'Directly in front of a garage which is integral with the residence structure'. A Zoning Board of Appeals agenda of March 18, 2026 sums it up: 'Parking within the minimum front yard is not permitted'. Section 43-134A(4) bars required parking within 10 feet of a street's right-of-way line, and section 43-134A(9) sets each space at 18 feet long by 8 1/2 feet wide or more. See Chapter 43's parking and driveway sections.
Patios and walls meet their own lines in the City's zoning. Section 43-33P(1)(a) lets 'An unroofed extension, deck or patio projecting not more than eight feet' sit in a required front yard, and section 43-33P(2)(f) permits 'Unroofed patios and decks less than three feet above finished grade' in side and rear yards. Coverage counts too: section 43-40D(2), as a Zoning Board of Appeals agenda quoted it on April 18, 2023, holds 'accessory residential uses and structures' to at most 75% of side and rear yards added together and at most 60% of the rear yard or of any single side yard. Fences and walls, retaining walls included, may rise no more than 4 feet in any required setback along a street or in a required front yard setback, and no more than 6 feet in other required setbacks (section 43-41D(3)(a)). Poured retaining walls have their own page.
Drainage, street trees and the clock shape the work as well. Section 56-57 of the City's Code requires that 'Final grading shall be such as to shed surface runoff away from buildings.' Section 80-10A makes it unlawful to remove, cut, break or injure a street tree without written permission from the City's Commissioner of Parks, Recreation and Conservation, and section 80-13 bars any 'stone, cement or other impervious material' that would cut off air and water to its roots without that permission. Section 66-4F restricts construction tools and equipment 'between the hours of 6:00 p.m. and 8:00 a.m. the following day' and 'at any time on weekends or legal holidays', and section 66-2 starts the weekend Friday at 6:00 p.m. and ends it Monday at 7:00 a.m.
- Steep slopes: once a site under review includes more than 5,000 square feet sloped steeper than 15%, City code section 43-105B(1) applies extra standards, among them retaining walls no higher than six feet within the setbacks.
- Lot coverage: maximum building coverage varies by zoning district under City code section 43-27, Table 43-3; one case on the Zoning Board of Appeals' March 18, 2026 agenda shows a 40% limit.
- Paving and drainage: City code section 43-134C(1) requires that parking areas be 'paved with an impervious surface in accordance with Yonkers building codes', and section 43-134C(2) wants each one 'drained so as to properly dispose of all surface water falling thereon.'
- Neighbors' land: City code section 58-17 says 'No person shall direct or divert the flow of any surface drainage' in or on a yard or the premises of a habitable building, or on the property of others.
- Dumpsters: one in the roadway or over a sidewalk needs an Engineering Department permit; one 'placed completely on private property' does not.
- Clear walks: City code section 91-34A has owners and occupants keep 'the sidewalk, flagging and curbstone' free from obstruction, and we keep the walk and street passable while we work.
- Noise exceptions: City code section 66-4F excepts emergencies and 'home construction projects by the homeowner', and section 66-10A lets the Commissioner of Housing and Buildings grant a variance.
- Stormwater: the City's stormwater article covers land development that disturbs one acre or more, or less as part of a larger common plan (section 43-215), which must file a stormwater pollution prevention plan before review.
Westchester County advice and New York State rules for concrete
A home improvement license comes first. In Yonkers, a permit to renovate an existing dwelling of 1 to 3 families requires a Home Improvement Contractor's License from the City's Consumer Protection Bureau, per the Department of Housing and Buildings, and City code section 31-129 bars running a home improvement business without one; section 31-133A, amended 6-1-2017, sets the fee at $400, and section 31-132A makes it good for two years. Westchester County's Department of Consumer Protection publishes the County's own licensing law and application and a sample home improvement contract, and its tips urge homeowners to confirm that a contractor has a license and to look for outstanding judgments or liens against the business. The pages we read do not say whether the County license also reaches work inside Yonkers; the County's Department of Consumer Protection can answer that.
General Business Law section 771, a State of New York statute, governs the home improvement contract itself. The contract 'shall be evidenced by a writing and shall be signed by all the parties to the contract'; it must be legible and in plain English, name the contractor with address, telephone number and any license number, give approximate or estimated dates for starting and for substantial completion, describe the work and materials, and state the agreed consideration. The owner may still cancel 'until midnight of the third business day after the day on which the owner has signed', and gets a copy before any work is done. Under Lien Law section 71-a(4), payments taken before substantial completion go to an escrow account 'within five business days' unless the contractor furnishes a bond, contract of indemnity or irrevocable letter of credit. See General Business Law section 771 on the State Senate's site.
Digging and sales tax have State rules too. The State Public Service Commission's one-call rule, 16 NYCRR Part 753, has an excavator give notice 'at least two but not more than ten working days' before digging, not counting the day of the call (section 753-3.1); we call 811 through UDig NY on that schedule, and UDig NY says a request 'has no cost to you'. The rule is reproduced on UDig NY's page for Part 753. On sales tax, the State Department of Taxation and Finance sorts concrete work in Publication 862: a new or completely replaced driveway, patio or sidewalk is a capital improvement, with Form ST-124 as the paperwork, while replacing sections or patching holes and cracks counts as taxable repair. Publication 718 puts the combined rate in the City of Yonkers at '8-7/8' percent from March 1, 2025.
- Code edition: the New York Department of State's notice requires permit applications submitted on or after December 31, 2025 to follow the 2025 Uniform Code; its residential volume, published July 2025, is titled 2025 Residential Code of New York State.
- Capital improvement test: the State's Tax Bulletin TB-ST-104 requires all three conditions: the work substantially adds value or appreciably prolongs the property's useful life, becomes part of the real property, and 'is intended to become a permanent installation.'
- Driveway lines: the State's Publication 862 files 'Installation or complete repaving (resurfacing) of driveways, parking lots, and walks' under capital improvements, and 'Replacing sections of concrete or blacktop driveways, parking lots, and walks' under taxable repairs.
- Checking a license: the State's contract law puts the contractor's license number in the contract, and questions or complaints about a contractor go to the City's Consumer Protection Bureau through its Consumer Help Line.
- Private lines: UDig NY says 'Utility companies do not always identify private utility lines', among them water services and sewer laterals.
- State highways: a driveway entrance within a State highway right of way needs a work permit from the commissioner of transportation under the State's Highway Law section 52.
Send us photos and measurements. Our written quote is free and names every Yonkers permit your concrete job needs.
Quick Answers
Do I need a permit to replace my driveway in Yonkers?
No building permit is needed if the replacement stays within the area the City of Yonkers has already approved. The City's building permit FAQ puts it this way: 'No. If you do not add to the areas already approved you may repave without a building permit.' A wider driveway falls outside that answer; for a new driveway or parking space, the same FAQ says 'Yes' and calls for a building permit. Separately, any piece of the job in the City's right-of-way needs an Engineering Department permit, and the Department's 2012 worksheet sets a $200 deposit for replacing an existing sidewalk or driveway.
Who is responsible for sidewalk repair in front of my house in Yonkers?
You are, as the owner of the property. Under the City of Yonkers Code, section 103-1 places the walk in front of each lot on its owner, and the City's property owner page says every sidewalk abutting a property 'must be kept in good repair and free of tripping hazards'. Once the Commissioner of Public Works has served a notice to repair, the owner has 30 days from service under section 103-3; if the owner does not act, sections 103-4 and 103-5 have the Commissioner do the repair and bill the owner. Any repair needs an Engineering Department permit before work starts.
How long do I have to clear snow from my sidewalk in Yonkers?
Six hours once a daytime snowfall stops; for snow that falls overnight, the deadline is 12:00 noon the following day. Both limits are in section 103-9 of the City of Yonkers Code, which covers the sidewalk's whole width and the abutting fire hydrants, and section 103-8 adds a three-foot area around each hydrant, measured from its center line. Shoveling, blowing or plowing the snow into a city street is a violation, the City's snow page says. Breaking the snow rules is a Class III offense under section 103-128, with a fine of up to $1,000 under section 1-21 (amended 6-26-2012).
Do I need a permit for a patio in Yonkers?
Not if it is new and covers 200 square feet or less. The City's building permit FAQ states: 'New Patios less than or equal to 200 square feet do not require a permit.' That exemption does not cover bigger patios, so for one over 200 square feet ask the Department of Housing and Buildings. Zoning applies whatever the size: the same answer warns of zoning rules on a patio's placement and dimensions, and City code section 43-33P(1)(a) limits a patio in a required front yard to a projection of no more than eight feet. A raised, structural platform counts as a deck in the FAQ's terms, and decks need a permit.
Do I need a permit for a retaining wall?
In Yonkers, the Department of Housing and Buildings decides: the City FAQ answers in our sources do not cover retaining walls, and the City code's fee sections have no line for them. City code section 56-15A requires a permit to build or alter 'any building or structure'. Unless a wall directly affects a regulated building, an accessible route or a means of egress, the State's Department of State treats it as exempt from the Uniform Code, and it warns that 'an exemption from the permit requirement does not constitute an exemption from the Uniform Code.' Either way, height has limits: walls may stand 4 feet tall in a front yard or street-side setback that zoning requires, and 6 feet tall in its other required setbacks (City zoning section 43-41D(3)(a)).
How much does a building permit cost in Yonkers?
A one- or two-family home pays a '$125 filing fee plus $15 per each $1,000 of the estimated cost' under section 56-18A(1) of the City of Yonkers Code, as last amended 6-25-2025. Other permits, for work estimated below $10 million, start from a $250 filing fee and add the same $15 for each $1,000. Section 56-20A splits the payment: half when the plans are filed, half when the permit is issued. Sidewalk and curb-cut permits from the Engineering Department carry their own deposits and fees, and starting work without a permit brings a penalty equal to twice the total permit fee due (section 56-19.1B).